2006 Construction Update

February 19, 2006

 

The New For 2006 Voyage Rollercoaster at Holiday World, Santa Claus, Indiana

They started running utilities to the new Thanksgiving section this week.  The pile of dirt that extends from the lower center of the picture that heads along the back of the employee lot is for utilities.

 The New For 2006 Voyage Rollercoaster at Holiday World, Santa Claus, Indiana

The Voyage's roof got done just in time for a nice dusting of snow that we had yesterday.  Also they have started siding the Pepsi Oasis/bathroom off to the left.

The New For 2006 Voyage Roller Coaster at Holiday World, Santa Claus, Indiana

Most of the work going on with The Voyage is either with the track or back up in the woods where you really can't get a clear view from the roads outside of the park.

The New For 2006 Gobbler's Getaway at Holiday World, Santa Claus, Indiana

It looks like the foundation for the Gobbler's Getaway building is about done.  I hear that once the foundation is done it will go up pretty quick which is good because there is just 75 days to go until opening.

That's all for this week.  Check back next week for more.

 

Click here for more Holiday World 2006 construction pages.

 